Mullaloo returning-client case study
Mullaloo Solar and Sigenergy Battery Upgrade for Stored Solar
A Mullaloo homeowner returned to Australis Solar to add 24kWh of Sigenergy battery storage to their existing 6.6kW Trina solar system. The original single-phase installation was completed in February 2025, followed by the battery addition in November 2025.
Our Perth-based, WA-owned team built on the existing 5kW Sigenergy system rather than replacing the solar array. Explore the two-stage installation below, or request an assessment of your own solar and battery options.
- 15 × Trina 440W panels retained
- Three 8kWh battery modules added later
- Battery storage for grid-connected use, without blackout backup in the recorded scope

Confirmed installation records
Mullaloo project snapshot
The original solar installation and later battery addition form two stages of the same property’s energy upgrade.
A practical two-stage upgrade
Customer objective and property considerations
The project evolved from replacing an older solar system to adding storage when the homeowner was ready.
Solar before storage
The original works replaced an older 2.4kW solar system with 15 Trina panels and a 5kW battery-ready Sigenergy inverter.
The homeowner initially chose solar without a battery, retaining a pathway to add storage later.
Roof-restoration sequencing
The original job was planned in stages around roof restoration: remove the old equipment and prepare the roof works, then return to complete the new solar installation.
This allowed the solar works and roof restoration to be coordinated at the same property.
A later return for batteries
The later completed job explicitly identifies the original solar installation and adds three battery modules and a power sensor.
The new scope provides storage for grid-connected operation. Blackout backup was not included.
Retain solar, add storage
Installed system and equipment
The later works added batteries and metering to the existing Sigenergy installation.
15 × Trina Vertex S+ 440W panels
The original 6.6kW array and Clenergy rails and racking were retained with the later battery works.
Explore solar panels →5kW single-phase Sigenergy inverter
The homeowner chose a battery-ready inverter during the original solar installation, providing the platform for the later storage addition.
Explore Sigenergy systems →Three 8kWh battery modules
The completed battery scope records 24kWh of Sigenergy storage. Battery energy capacity differs from available output power, which is limited by the equipment and operating settings.
Explore solar batteries →Single-phase Sigen Power Sensor
The battery addition included a Sigen Power Sensor with an external current transformer to support system energy measurement and control.
Explore solar upgrades →The installation decisions
Challenges and Australis Solar solutions
Roof sequencing, equipment retention and a clear battery scope shaped this project.
Coordinate solar with roof restoration
Challenge
The old system needed removal and roof restoration was planned.
Australis Solar assessment
The solar job notes set out separate preparation and completion visits.
Australis Solar solution
Sequence the removal and preparatory works before the roof restoration, then complete the rails, panels and inverter installation.
Build on the first installation
Challenge
The homeowner later wanted batteries for the solar system already installed.
Australis Solar assessment
The battery job identifies the original 6.6kW Trina array and 5kW Sigenergy inverter.
Australis Solar solution
Retain the existing solar platform and add three 8kWh battery modules with single-phase energy metering.
Keep the backup scope clear
Challenge
Battery storage can be mistaken for guaranteed power during a blackout.
Australis Solar assessment
The completed battery scope expressly excludes backup power to house circuits during grid failure.
Australis Solar solution
Describe this as a grid-connected battery addition. Assess any future backup request separately, including switching hardware, electrical configuration and appliance loads.
Solar and the later battery stage
Mullaloo installation gallery
Existing project photographs show the solar array, original controller position and later controller-and-battery arrangement.




Mullaloo project questions
Solar and battery upgrade FAQs
Was the battery installed with the original solar system?
No. The original solar installation was completed in February 2025. The later battery addition was completed in November 2025.
How much solar and storage does the recorded system have?
The original array is 6.6kW, using 15 Trina 440W panels. The later battery job records three 8kWh Sigenergy modules, totalling 24kWh.
Was the existing solar system replaced again for the batteries?
The battery scope identifies the existing 6.6kW solar array and 5kW Sigenergy inverter. It adds battery modules and a single-phase power sensor rather than another solar array.
Does this battery addition provide blackout backup?
No blackout backup was included in the recorded battery scope. Battery storage alone should not be taken as confirmation that house circuits will stay powered during a grid outage.
What savings has the battery achieved?
Measured savings are not available for this case study. Actual results depend on solar generation, usage timing, tariffs and system settings. Earlier proposal estimates are not presented as measured battery results.
Can I add a battery to my Perth solar system?
Australis Solar assesses the exact inverter and panels, electricity use, switchboard, battery location, backup requirements and future plans. Quotes are subject to a site visit and switchboard inspection.
Request a property-specific design
Plan the next stage of your Perth solar system
Send us your latest Synergy bill and details of your existing solar. Our team will assess your usage, generation, inverter, switchboard, battery location, backup needs and future EV plans before recommending an upgrade.