Bassendean installation case study
Bassendean Solar installation
This Bassendean installation combined 13.2kW of Trina panels with a 10kW three-phase Fronius Symo inverter and Fronius Smart Meter. The project required cable routing through a tight roof cavity, considered panel alignment and an inverter position on the south-facing wall.

Installation specifications
Bassendean project snapshot
Location
Bassendean, WA
Installation year
2025
Solar capacity
13.2kW
Solar panels
30 × Trina Vertex S+ N-Type Mono Dual Glass 440W panels
Inverter
Fronius Symo 10kW three-phase inverter
Additional equipment
Fronius Smart Meter 50kA-3, three-phase with /5A CT
Additional equipment
External eight-pole enclosure within the switchboard box
Designed for this property
Customer objective and design considerations
Roof cavity access
The limited roof space required a planned cable route using three entry manholes.
Panel alignment
Landscape rotation was considered to improve panel alignment with the roof screw lines.
Inverter location
The inverter was installed on the south-facing wall near the clothesline, with surface conduit.
Meter installation
The electrical scope included a Fronius Smart Meter and an external eight-pole enclosure within the switchboard box.
Installed equipment
System design and installed components
Solar array
30 × Trina Vertex S+ N-Type Mono Dual Glass 440W panels provide 13.2kW of installed panel capacity.
Inverter
Fronius Symo 10kW three-phase inverter.
Installation equipment
Fronius Smart Meter 50kA-3, three-phase with /5A CT.
Installation equipment
External eight-pole enclosure within the switchboard box.
Project energy and savings figures
- Annual generation: 17,691kWh per year
- Energy offset: 167%
- Estimated savings: $1,533.36 per year
Project-specific installation work
Challenges and Australis Solar solutions
Tight roof cavity
Challenge
Limited space complicated the cable runs.
Australis Solar assessment
The installation needed accessible entry points for the wiring route.
Australis Solar solution
Three entry manholes were used to manage the cabling.
Panel alignment
Challenge
Roof screw lines influenced panel-layout planning.
Australis Solar assessment
The design team considered landscape rotation for alignment.
Australis Solar solution
Panel orientation was reviewed for alignment with the roof fixing positions.
Inverter placement
Challenge
The project required an accessible equipment position and cable route.
Australis Solar assessment
The south-side wall near the clothesline was selected.
Australis Solar solution
The Fronius inverter was mounted on that wall using surface conduit.
Installation photographs
Bassendean installation gallery




Bassendean project questions
What solar panels were installed in Bassendean?
30 × Trina Vertex S+ N-Type Mono Dual Glass 440W panels, providing 13.2kW of solar capacity.
Which inverter was installed?
Fronius Symo 10kW three-phase inverter.
What affected the installation design?
The limited roof space required a planned cable route using three entry manholes. Landscape rotation was considered to improve panel alignment with the roof screw lines. The inverter was installed on the south-facing wall near the clothesline, with surface conduit. The electrical scope included a Fronius Smart Meter and an external eight-pole enclosure within the switchboard box.
Request a property-specific design
Planning solar in Bassendean?
Australis Solar is Perth-based and WA-owned, operating since 2008. Send us your Synergy bill and property details so the system can be assessed around your roof, electricity use, existing electrical equipment and future battery or EV plans.
Explore solar panels for Perth homes, battery storage and upgrades to existing solar systems.